After 15 days of testimony, the Peoria County Zoning Board of Appeals recommended denying Repsol Renewables’ proposed Four Creeks Wind Project. The panel also approved a set of possible conditions to send with the application to the full County Board, leaving the project’s fate undecided ahead of a Nov. 5 meeting.
Key takeaways
- The zoning board voted 4-2 to recommend denying the wind farm application.
- The proposed project would include 113 turbines across northwest Peoria County.
- The board also voted to forward possible approval conditions for County Board consideration.
The two votes leave county officials to weigh a recommendation against denial alongside conditions that could allow the project to proceed.
A divided recommendation
The board’s decision came after a four-hour session for final testimony and closing arguments. Greg Happ, Steven Pollack, Tom Modlin and Rob Culp voted to recommend denial; chairperson pro tem Steve Schmitt and Richard Burns opposed the recommendation. Some in the audience briefly applauded after the vote.
Before the roll call, county attorney Andy Keyt noted that the board had already determined the applicant met sound requirements in the existing county code. The board’s findings of fact nevertheless included sound regulation among four of seven areas it determined had not been satisfied, reflecting differences in how members weighed the application’s requirements.
Project proposed for northwest Peoria County
Repsol Renewables wants to develop the Four Creeks Wind Project, a large-scale wind farm with 113 turbines. The proposed footprint extends from the Brimfield and Princeville areas toward the Knox and Stark county lines.
The zoning board’s recommendation followed 15 days of testimony. Some members indicated that certain findings could be addressed through revisions to the proposal and believed the project might still move forward.
County Board decision is next
The zoning board voted to include possible approval conditions in the materials it will send to the full Peoria County Board. That vote followed its recommendation to deny the application, so the project remains under consideration rather than being definitively rejected.
The County Board is scheduled to consider the application at its Nov. 5 meeting. Its decision will determine whether the proposed wind farm can proceed, potentially subject to conditions.